Rain today so time to check on the boats we have in storage at an off-site location. They are still covered and appear ok although some trailer tyres require a bit more air.
Friday, 7 August 2026
It's wet
Friday, 31 July 2026
Quiet Summer Time
Work slows down during the summer months as volunteers go away are on holiday.
We spent a while separating out scrap materials and pulling up weeds outside.
Work is continuing on the elliptical stern yole Laverne
Friday, 10 July 2026
Odds and Sods week
Several of our overhead light strips have stopped working but many are not easily accessible because of the boats stored underneath them. However, we managed to make enough space to fix one unit.
A final coat of paint was applied to Venture's rudders and dagger boards.
Friday, 3 July 2026
Finishing things off
The centre board on Saga has finally been rigged with an arrangement that is representative of what it would have originally looked like. The original centre board was steel and heavy so required some mechanical assistance to lift it.
Blocks for the main sheet have also been attached although we haven't pulled the mainsheet in as this would make manoeuvring the boom more difficult.
Finishing touches were made to the Groat dingy.
Discussion about where the various fittings went on Venture.
Fitting the wheels to one of the new dinghy frames.
Friday, 26 June 2026
Space Manegement
Storage space is always a problem as we do not have enough of it. We have already constructed a number of steel frames to allow some of the smaller boats to be double stacked but we really needed more frames. Two more steel frames have now been constructed with a wider spread which will allow further boats to be stacked. This week the frames were getting painted, wheels will then be fitted and the frames will then be ready for use.
Friday, 19 June 2026
It's Getting Hot
As the next heat wave hits the country, 15C in Orkney, work on Venture includes painting of dagger boards and rudders and sorting through the fittings to see what goes where on the hulls.
Following a visit from members of UHI (University of the Highlands and Islands) to catalogue the Labradorite stones have in our care, we have put the stones back in storage.
While the weather outside was not too bad we did some weeding.
Wednesday, 17 June 2026
Aldis Lamp
Work on refurbishing the Aldis Lamp has been completed. The box has been stripped and repainted and all fittings repaired or replaced as best we can. The lamp itself has been left untouched except for a clean as it works.
Friday, 5 June 2026
Refurbishment & Protection
A 1936 Aldis Lamp & storage case is being refurbished - the lamp still works.
Friday, 29 May 2026
Spring Cleaning
We needed to extract our Labradorite rocks from the back of a storage area to allow the local archaeology dept to catalogue all the stones. This operation required us to move a lot of other materials so we took the opportunity to sort out the worth keeping from bruck.
Bruck has been put aside to be checked again before we recycle or dispose of.
Along the way we recovered the spray decks for Laverne. These spray decks can be attached to the boat usually in stronger winds to allow a greater angle of heel without the risk of down flooding into the cockpit. A flip up section allows the crew to sit comfortably on the windward side.
Friday, 22 May 2026
Sag
Cingalee has a slight sag towards her bow where the weight of the foredeck adds to the load on the keel. To address this problem we have added additional support under the sides of the hull and relieved the load on the keel.
Saturday, 16 May 2026
Nameplates
The nameplate from Laverne has been refurbished. Although probably not the sort of nameplate that a boat builder would have installed it is what was on the boat when OHBS took over custodianship so we have kept it.
The builders plate on the dinghy Ruby II has also been cleaned up. It was covered in old varnish and although now a lot cleaner some varnish residue still remains.
| Before |
| After |
OHBS recently held an Open Day so that visitors could see what work was going on and the results of past work.
Friday, 8 May 2026
Spring Cleaning
With visitors expected this afternoon and an open day next week a bit of spring cleaning was order of the day.
Laverne, which had been lying on her side to allow easier access to the underside was righted.
The Yachting World Catamaran Venture has a damaged dagger board. We will splice in a new piece of wood and shape to match.
Saturday, 25 April 2026
Going, Going, Gone
Friday, 17 April 2026
Back to work
The 50 year old compressor we acquired is not worth keeping so we have dismantled it into manageable parts for recycling.
Work continues on the exterior of Laverne which is now heeled over to make for easier access.